LGU-BISLIG INFRASTRUCTURE PROJECTS

 
Slide 1
Construction/Rehabilitation of Cassava Drying Center

Location: San Isidro. Bislig City

Location: San Isidro, Bislig City
Completion Date: October 10, 2020
Status: 100% Physical Completion

P 500,000.00
Slide 2
Construction of Perimeter Fence at Hilltop Elementary School

Location: Hilltop Elementary School. Bislig City

Location: Hilltop Elementary School, Bislig City
Completion Date: March 25, 2020
Source of Funds: Special Education Fund
Status: 100% Physical Completion

P 384,590.00
Slide 3
Construction of Fruit Stalls

Location: Market Site, Mangagoy, Bislig City

Location: Market Site, Mangagoy, Bislig City
Completion Date: January 13, 2020
Status: 100% Physical Completion

P 249,838.00
Slide 4
Construction of Negokart/Pushcart

Location: Poblacion, Bislig City

Location: Poblacion, Bislig City
Completion Date: October 10, 2020
Source of Funds: DOLE
Status: 100% Physical Completion

P 500,000.00
Slide 5
Rehabilitation of Health Station

Location: Market Site, Mangagoy, Bislig City

Location: Market Site, Mangagoy, Bislig City
Completion Date: July 30, 2019
Source of Funds: BUB 2016
Status: 100% Physical Completion

P 125,000.00
Slide 6
Construction of Multi-Purpose Drying Pavement

Location: Cumawas, Bislig City

Location: Cumawas, Bislig City
Completion Date: October 2, 2019
Source of Funds: 20% EDF 2019
Status: 100% Physical Completion

P 310,000.00
Slide 7
Completion of Day Care Center

Location: San Jose, Bislig City

Location: San Jose, Bislig City
Completion Date: March 10, 2020
Source of Funds: DSWD Grant
Status: 100% Physical Completion

P 400,000.00
Slide 8
Installation of Solar Pumps and Panels at Sote

Location: Sitio Sote, Bislig City

Location: Sitio Sote, Bislig City
Completion Date: March 10, 2020
Status: 100% Physical Completion

P 160,000.00
Slide 9
Renovation of Sote Elementary School Stage

Location: Sote Elementary School, Bislig City

Location: Sote Elementary School, Bislig City
Completion Date: July 30, 2020
Source of Funds: Support to Exec. INGO
Status: 100% Physical Completion

P 29,464.50
previous arrow
next arrow
 
Slide 1
Construction of Barbeque Stalls

Location : Marketsite, Mangagoy, Bislig City

Location : Marketsite, Mangagoy, Bislig City
Source of Fund : 20% EDF CY - 2019
Implementa-tion : Admin. Project
Status : 36.39% Physical Completion

P 200,000.00
Slide 2
Backfilling of Coastal Road at Danipas

Location : Sitio Danipas, Brgy. Labisma, Bislig City

Location : Sitio Danipas, Brgy. Labisma, Bislig City
Source of Fund : Construction of DRRM – Trust Fund
Implementa-tion : Admin. Project
Status : 83.00% Physical Completion

P 1,000,000.00
Slide 3
Construction of Barbeque Stalls

Location: Market Site, Bislig City

Location: Market Site, Bislig City
Source of Funds: 10% CIP-2018
Status: Pending due to unavailability of woods

P 309,356.00
Slide 4
Perimeter Fence

Location: COAFC, Bislig City

Location: COAFC, Bislig City
Source of Funds: Bayanihan Support (Supplemental # 0361899682)
Status: 90% Physical Completion

P 380,000.00
Slide 5
Slope Protection of San Isidro

Location: Brgy. San Isidro, Bislig City

Location: Brgy. San Isidro, Bislig City
Source of Funds: Support to BDRRM
Status: 40% Physical Completion

P 500,000.00
Slide 6
Rehabilitation of Roads and Slope Protection

Location: Brgy. San Antonio, Bislig City

Location: Brgy. San Antonio, Bislig City
Source of Funds: Special Trust Fund CY 2014
Status: For Blow Top

P 500,000.00
previous arrow
next arrow
 
Slide 1
Construction of Drainage Canal at F. Clar St., P. Castillo St. and St. Paul District

Location : Mangagoy, Bislig City

Location : Mangagoy, Bislig City
Source of Fund : 20% EDF
Contractor : RMF Construction
Date Started : December 21, 2017
Date Completed : March 21, 2018

P 960,005.55
Slide 2
Construction of Drainage Canal at P-4 Castillo Village

Location : Mangagoy, Bislig City

Location : Mangagoy, Bislig City
Source of Fund : 20% EDF
Contractor : RMF Construction
Date Started : December 21, 2017
Date Completed : March 21, 2018

P 405,505.90
Slide 3
Construction of Drainage Canal at P-3 Panaghiusa District

Location : Mangagoy, Bislig City

Location : Mangagoy, Bislig City
Source of Fund : 20% EDF
Contractor : RMF Construction
Date Started : December 21, 2017
Date Completed : March 21, 2018

P 299,293.60
Slide 4
Concreting of Road Post 12 to
Sug-obon

Location : Tabon, Bislig City

Location : Tabon, Bislig City
Source of Fund : 20% EDF CY – 2018
Contractor : RNH Bentulan Construction
Date Started : January 19, 2018
Date Completed : August 9, 2018

P 3,324,144.54
Slide 5
Construction of Multi-Purpose Dormitory Building

Location : COAFTC, Sta. Cruz, Bislig City

Location : COAFTC, Sta. Cruz, Bislig City
Source of Fund : Supplemental Budget #1 CY 2018
Contractor : L.M. Construction and General Marketing
Date Started : May 19, 2018
Date Completed : October 17, 2018

P 11,625,788.89
Slide 6
Construction of Feedmill Building

Location : COAFTC, Sta. Cruz, Bislig City

Location : COAFTC, Sta. Cruz, Bislig City
Source of Fund : Supplemental Budget #1 CY 2018
Contractor : JB Ciano Construction
Date Started : July 30, 2018
Date Completed : October 27, 2018

P 3,860,721.91
Slide 7
Concreting of GK Bonggaitan Road

Location : Mangagoy, Bislig City

Location : Mangagoy, Bislig City
Source of Fund : 20% EDF
Contractor : RMF Construction
Date Started : August 13, 2018
Date Completed : December 20, 2018

P 930,331.82
Slide 8
Proposed Perimeter Fence

Location : COAFTC, Sta. Cruz, Bislig City

Location : COAFTC, Sta. Cruz, Bislig City
Source of Fund : Supplemental Budget #1 CY – 2018
Contractor : LM Construction & General Marketing
Date Started : August 2, 2018
Date Completed : fEBRUARY 28, 2019

P 3,773,709.63
previous arrow
next arrow
 
Slide 1
Construction of Bislig City 911 Operation Center

Location: National Highway, Poblacion, Bislig City

Location: National Highway, Poblacion, Bislig City
Contractor: Jimberns Builders & Construction Suppplies
Date Started: April 4, 2019
Completion Date: September 9, 2020
Source of Funds: CDRRMF Fund
Status: 66% Physical Completion

P 20,765,812.67
Slide 2
Construction of Multi-Purpose Open Gym

Location : BCES, Brgy. Poblacion, Bislig City

Location : BCES, Brgy. Poblacion, Bislig City
Source of Fund : 20% EDF CY 2020
Contractor : BEBCON Builders & Supply
Status : Suspended as of February 17, 2021 due to Electrical Works to be performed by SURSECO

P 1,396,710.97
Slide 3
Construction of Drainage Canal at Purok 2, Castillo Village

Location : Castillo Village, Mangagoy, Bislig City

Location : Castillo Village, Mangagoy, Bislig City
Source of Fund : 20% EDF CY - 2019
Contractor : MAX C Engineering and Construction Services
Status : 95% Physical Completion
Date Started : February 1, 2021
Date of Completion : August 3, 2021

P 2,806,783.73
Slide 4
Completion of Archive Building

Location : City Hall Premises

Location : City Hall Premises
Source of Fund : 20% EDF CY 2020
Contractor : ROIM Builders and Construction Supply
Status : 78% Physical Completion
Date Started : November 16, 2020
Date of Completion : August 4, 2021

P 5,013,886.17
Slide 5
Completion of B.O.S.S. Center

Location : Marketsite, Mangagoy, Bislig City

Location : Marketsite, Mangagoy, Bislig City
Source of Fund : 20% EDF CY 2020
Contractor : ROIM Builders and Construction Supply
Status : 74.89% Physical Completion
Date Started : November 16, 2020
Completion Target : August 4, 2021

P 5,192,371.56
Slide 6
Baywalk Development of Poblacion, Bislig City (Phase II)

Location: National Highway, Poblacion, Bislig City

Location: National Highway, Poblacion, Bislig City
Contractor: BEBCON Builders and Supply
Date Started: January 5, 2021
Completion Date: August 3, 2021
Source of Funds: Local Government Support Fund Assistance
Status: 66.17% Physical Completion

P 10,849,260.76
Slide 7
Construction of Legislative Phase 1

Location : City Hall Premises, Bislig City

Location : City Hall Premises, Bislig City
Source of Fund : Loan
Contractor : RELY Construction & Supply
Status : 6% Physical Completion
Date Started : May 7, 2021
Completion Target : February 25, 2023

P 67,757,505.34
previous arrow
next arrow
 
Slide 1
Construction of Poblacion Seawall

Location: San Isidro. Bislig City

Location: Guava Junction, Bislig City
Source of Funds: TF-LDRRMF & 20% EDF CY-2020S
Status: Negotiated Procurement (Adjacent or Contiguous)

P 4,100,000.00
Slide 2
Installation of Streetlights for Major Roads

Location: San Isidro. Bislig City

Location: After San Fernando Bridge going to COAFC
Source of Funds: 20% EDF CY 2020
Status: Waiting for Notice of Award

P 7,350,000.00
Slide 3
Rehabilitation of Manpower Skills Training Center

Location: San Isidro. Bislig City

Location: National Highway, Poblacion, Bislig City
Source of Funds: 20% EDF CY 2020
Status: Opening of Bids on September 20, 2020

P 5,000,000.00
Slide 4
Construction of Multi-Purpose Open Gym

Location: San Isidro. Bislig City

Location: BCES, Poblacion, Bislig City
Source of Funds: 20% EDF CY 2020
Status: Issuance of Notice to Proceed

P 1,500,000.00
Slide 5
Completion of B.O.S.S. Center

Location: San Isidro. Bislig City

Location: Market Site, Bislig City
Source of Funds: 20% EDF CY 2020
Status: Post-Qualification Investigation Report by BAC-TWG

P 5,500,000.00
Slide 6
Completion of Archive Building

Location: San Isidro. Bislig City

Location: City Hall Premises, Bislig City
Source of Funds: 20% EDF CY 2020
Status: Opening of Bids on September 15, 2020

P 5,500,000.00
Slide 7
Proposed City Hall Extension Building

Location: San Isidro. Bislig City

Location: City Hall Premises, Bislig City
Source of Funds: Loan
Status: On-Going Preparation of Program Works

P 80,000,000.00
previous arrow
next arrow